HIGHLIGHTS:
•
Completion of Design Feasibility Report, advancing solar farm and transmission system to a 30% level of concept
design.
•
Peak export hydrogen volume revised to 90,000 tpa, with a +/- 10,000 tpa allowance for future optimisation activities.
•
Northern Territory Environment Protection Authority (NTEPA) finalises the EIS Terms of Reference, including the
Federal Government EPBC requirements.
•
Preparation of the EIS continues with submission now planned for early 2024, covering both the Northern Territory
and Federal Government EPBC approval processes.
•
Draft project and land agreements submitted to the Tiwi Land Council, together with a proposed community benefits
package.
•
Progress on Port Melville has been delayed as NT Port & Marine Pty Ltd, the Port sublessee and operator, has been
placed into Administration. Provaris is in communication with Deloitte, the administrator, and other relevant parties
to monitor and assess the near term direction of Port Melville.
•
Joint venture process to secure project partners is underway.
Provaris Energy Ltd (ASX.PV1) (Provaris, or the Company) is pleased to share the latest developments regarding
the Tiwi H2 green hydrogen export project on the Tiwi Islands, Northern Territory. The Company continues to make
significant progress through its Early Works program initiated in late 2022 that cover detailed engineering, permitting and
land and project agreements.
Garry Triglavcanin, Provaris Executive Director & Chief Development Officer, commented: “Provaris continues
to progress its Tiwi H2 project, and we are pleased with the detailed work undertaken to date by our Owner’s Engineer
(CE Partner) on the solar farm and transmission system and EcOz, our environmental consultant.
The key focus for Provaris is progression of the project and land agreements with relevant key Tiwi Island stakeholders.
Once a satisfactory outcome has been achieved, FEED and further engineering studies are planned to drive the project
toward financial close, targeted for the end of 2024.
With the support of key stakeholders, the project development program still allows for Provaris’ targeted first hydrogen
production and export in late 2027.”
Martin Carolan, Provaris Chief Executive Officer, highlights: “ The Tiwi H2 project is a first for the Australian
hydrogen industry, with the ambition to efficiently export compressed hydrogen, a gaseous green hydrogen that is a
pipeline ready high purity gas, simple to discharge for unloading, and an efficient delivery model to kick-off the
decarbonization of targeted downstream industries in SE Asia.
Provaris welcomes the Federal Government’s recent announcement of the Hydrogen Headstart funding program for export
projects and looks forward to participating in the consultation and future growth of such subsidy schemes designed to
accelerate large scale hydrogen export projects in Australia.”
ACN 109 213 470 |
WWW.PROVARIS.ENERGY | ASX.PV1
Design Feasibility Report advances the concept design of the solar farm and transmission system to a
30% level, providing the basis for optioneering and design optimisation.
Significant feasibility work and reporting has been undertaken, including the Owner’s Engineer’s (CE Partners)
completion of the Design Feasibility Report for the proposed solar farm and transmission system. The Design
Feasibility Report advances the concept design of the solar farm and transmission system to a 30% level, providing
the basis for optioneering and design optimisation.
The Design Feasibility Report assesses the proposed 2,640 ha Solar Precinct area, with the key outcomes concluding:
>
the Solar Precinct area supports 2,600 MWp of solar capacity;
>
the preferred solar system is a single axis tracking system;
>
annual generation is assessed to be over 5,000 GWh, delivered to the HV transmission system; and
>
a four circuit, 275kV transmission line is proposed from the Solar Precinct to the Hydrogen Production and
Export Precincts, being a distance of ~30km.
Modelling of the generation outcomes above, has led to the expected peak hydrogen production and export volume
for the Tiwi H2 project being revised to 90,000 tpa, with a +/- 10,000 tpa allowance for planned optimisation
processes, which will include the targeting of a reduction in identified power losses and further evaluation of
equipment design and selection.
Permitting and preparation of the EIS continues
As previously announced, on 26 April 2023, the NTEPA finalised and issued its EIS ”Terms of Reference”, which can
be viewed on the NTEPA’s website (see below). The Terms of Reference has also been finalised for the Federal
Government EPBC process. A joint EIS will be developed through to final approvals and lodged in early 2024.
NTEPA website: https://ntepa.nt.gov.au/your-business/public-registers/environmental-impact-assessments-register
Project Land Agreements submitted to Tiwi Land Council
Provaris has provided the Tiwi Land Council with its proposed draft project and land agreements for review and
comment. The draft agreements, amongst other things, include details of the proposed annual multi-million dollar
community benefits package that the Tiwi H2 project could deliver to the Munupi Clan and Tiwi Island people.
Provaris is also communicating with the Office of Township Leasing regarding Provaris’ commercial sublease
application for the Hydrogen Production and Export Precincts.
Port Melville
The sublessee and operator of Port Melville remains in “administration”, with Deloitte appointed as “administrator”
in late 2022. The administration has slowed Provaris’ progress in relation to several key port and export related
activities as Deloitte’s role is primarily that of a caretaker, pending resolution of the future direction of Port Melville.
Provaris is monitoring the position closely, including direct dialogue with Deloitte and other relevant parties.
Next Steps
•
•
•
•
Environmental Consultants to continue with the preparation of the EIS, with submission scheduled for early
2024. The draft submission will cover both the Northern Territory and Federal Government EPBC approval
processes.
Provaris’ key focus for 2023 is to achieve a satisfactory outcome with the Tiwi Land Council, Tiwi Plantation
Corporation, Office of Township Leasing and Deloitte (Port Melville) regarding the contractual agreements and
land access required for the Tiwi H2 project.
Subject to achieving satisfactory progress in relation to the contractual and land access arrangements, Provaris
will then commence the Front-End Engineering Design (FEED) and other engineering studies/activities on
country, including an overall geotechnical, hydrological and earthing/lightning program and the commencement
of solar monitoring.
Discussions with potential joint venture partners for project development through to FEED and a future final
investment decision.
www.provaris.energy
Page 2
Illustration of H2 Export Project, Melville Island, Tiwi Islands, Northern Territory.
To view a short animation video of the Tiwi H2 project please click the image below.
- END –
This announcement has been authorised for release by the Board of Provaris Energy Ltd.
Norm Marshall
Company Secretary
+61 481 148629
nmarshall@provaris.energy
ASX.PV1
Martin Carolan
Managing Director & CEO
+61 404 809019
mcarolan@provaris.energy
@ProvarisEnergy
Melanie Singh
NWR Communications
+61 439 748 819
melanie@nwrcommunications.com.au
Provaris Energy Ltd.
info@provaris.energy
Perth | Sydney | Oslo
About Provaris Energy
Provaris Energy Ltd (ASX: PV1) | www.provaris.energy
Provaris Energy (ASX: PV1) is an Australian public company developing a portfolio of integrated green hydrogen
projects for the regional trade of Asia and Europe, leveraging our innovative compressed hydrogen bulk storage and
carrier. Our focus on value creation through innovative development that aligns with our business model of simple
and efficiency hydrogen production and transport can establish an early-mover advantage for regional maritime
trade of hydrogen and unlock a world of potential. In August 2022 Provaris Norway AS was established to advance
the development of hydrogen export projects from Norway and other European locations.
Disclaimer: This announcement may contain forward looking statements concerning projected costs, approval timelines,
construction timelines, earnings, revenue, growth, outlook or other matters (“Projections”). You should not place undue reliance
on any Projections, which are based only on current expectations and the information available to Provaris. The expectations
reflected in such Projections are currently considered by Provaris to be reasonable, but they may be affected by a range of
variables that could cause actual results or trends to differ materially, including but not limited to: price and currency fluctuations,
the ability to obtain reliable hydrogen supply, the ability to locate markets for hydrogen, fluctuations in energy and hydrogen
prices, project site latent conditions, approvals and cost estimates, development progress, operating results, legislative, fiscal and
regulatory developments, and economic and financial markets conditions, including availability of financing. Provaris undertakes
no obligation to update any Projections for events or circumstances that occur subsequent to the date of this announcement or
to keep current any of the information provided, except to the extent required by law. You should consult your own advisors as
to legal, tax, financial and related matters and conduct your own investigations, enquiries and analysis concerning any transaction
or investment or other decision in relation to Provaris. $ refers to Australian Dollars unless otherwise indicated.
9 www.provaris.energy
WWW.PROVARIS.ENERGY
Page 3
Share your feedback
Discover