March 2024 Quarterly Activities & Appendix 4C Cash Flow
Released
Released
Announcement PDF
| March 2024
Provaris Energy Ltd (ASX: PV1, Provaris, the Company) is pleased to provide the following summary of the
Company’s development activities for the quarter that ended 31 March 2024.
H2NEO SHIPPING APPROVALS & PROTOTYPE TANK DEVELOPMENT
•
•
•
•
•
•
•
World-leading Classification Society DNV engaged to issue a Front-End Engineering Design Statement for Provaris’
proprietary H2Neo carrier design and approval of its proprietary hydrogen prototype tank.
Following extensive design and pre-production activities, a groundbreaking milestone was achieved with the
commencement of fabrication for the H2Neo carrier prototype tank, signifying a major step forward in Provaris’
innovative and proprietary hydrogen storage and marine transportation solutions.
Successful testing will secure Class Approval for the H2Neo carrier, a world-first achievement in bulk-scale
hydrogen marine transportation.
Final Class Approvals from marine classification societies DNV and ABS will mark a significant milestone and
accelerate the development of Provaris’ hydrogen value chain in collaboration with major energy and trading
companies across Europe.
Prototype tank completion also unlocks an early revenue venture identified through the production and sale of
smaller-scale hydrogen tanks from Norway to EU based industrial users of hydrogen, in late 2024.
Design optimization program for the full-scale H2Neo carrier containment tank has identified the potential for a
remarkable 30% weight reduction, promising lower build cost, enhanced propulsion efficiency, reduced fuel
consumption, and lower emissions.
Updated H2Neo ship outline and specification provides flexibility during construction and installation of tanks, and
increased reach and competition amongst shipyards.
EUROPEAN SUPPLY CHAIN DEVELOPMENTS
•
Further momentum in end user interest with the third signing of an MOU with a prominent international energy
company, underlining growing interest from European utilities in our compressed hydrogen solutions.
•
Post quarter end, further traction was made with a pioneering collaboration agreement with Global Energy Storage
(GES) to develop a new gaseous hydrogen import facility at the GES terminal in the Port of Rotterdam, Netherlands.
NORWAY COLLABORATION FOR H2 SUPPLY
•
Completion of the collaboration and prefeasibility study with Gen2 Energy for the Afjord project in Norway
demonstrated a competitive delivered cost of hydrogen to Europe using the Provaris’ H2Neo carriers.
•
Post quarter end, Provaris announced the extension of our partnership with Norwegian Hydrogen, building on the
successful feasibility work completed in Norway, with Finland added to the export locations being jointly evaluated
in the Nordics.
P rovaris M anaging Director and CEO, M artin Carolan, com m ented: “The March quarter has been a pivotal
period in the lead up to the commencement of fabricating a world first compressed hydrogen prototype tank. Our
unique proprietary tank design ‘unlocks’ significant market opportunity for low-cost storage and transport for shipping
and other industrial storage applications creating potential for early commercialisation of proprietary tank IP late 2024.
Provaris continues to receive strong engagement from hydrogen supply developers and demand for alternative
pathways to import hydrogen into Europe, which is evidenced by the continued growth in MOUs with major utilities
focused on alternatives to reduce delivered cost and address the uncertainty in other technologies and timelines.
Compression is now recognized as a low-cost approach to deliver bulk scale hydrogen before 2030. The addition of
our collaboration with GES for a hydrogen import terminal can provide market access to industrial users in Rotterdam
and further into the European network.
Europe continues to demonstrate leadership in developing the hydrogen economy and that is evident with further
announcements made by industry for hydrogen industrial offtake tenders and ongoing regulatory and financing
initiatives announced to assist the industry towards FID for early large-scale projects.”
”
www.provaris.energy
1
Quarterly Activities Report – March 2024
Construction of Prototype Tank underway
Fabrication for the H2Neo carrier prototype tank commenced during the March quarter. The commencement of
fabrication and testing is a groundbreaking milestone, with Provaris’ prototype scale compressed hydrogen tank a world
first.
Construction will use advanced automation and robotic laser-welding and will mark a significant step forward in
showcasing the safety and performance benefits of Provaris' proprietary tank design, which utilizes multiple layers of
carbon steel plate and an inner stainless-steel liner.
In early January 2024, Provaris engaged DNV to issue a Front-End Engineering Design Statement for the design and
approval of its proprietary hydrogen prototype tank.
By mid-2024, upon successful testing, final Class Approvals from marine classification societies DNV and ABS will be
obtained, marking a significant milestone and accelerating the development of hydrogen value chains in collaboration
with major energy and trading companies across Europe.
Fabricated at Prodtex's facility in Fiskå, Norway, the prototype tank showcases Provaris' proprietary design, utilizing
layered carbon steel and a stainless-steel liner. With dimensions of approximately 2.5m diameter and 9m length, it
boasts a capacity for 650 kg of hydrogen at a design pressure of 250 barg. Testing will confirm the full-scale tank design
can safely store hydrogen through a set of fatigue and over pressurization tests representative of 25 years of operations.
Location of Prodtex’s fabrication facility, in Fiska (Norway) and Illustration of the prototype tank
Copyright: Provaris Energy Ltd
Copyright: Prodtex AS
Development of early commercialistion of IP through small-scale tank production in 2024
Importantly, the completion of fabrication and testing will lead to the development of an early revenue opportunity in
2024 with the focus to also include the production and sale of smaller-scale hydrogen tanks to cater to a wide range of
applications, including maritime bunkering and industrial storage.
For the hydrogen industry to scale-up, there is a need for high quality carbon steel hydrogen tanks that focuses on
safety in operation, whilst delivering a low-cost and energy efficient storage solution. Final approvals will radically
advance the opportunities available to Provaris for the immediate need for industrial storage and the supply and
transport of gaseous hydrogen.
Additionally, further validating our innovative approach to hydrogen technology; during the March quarter Provaris
secured support from the Research Council of Norway under the SkatteFUNN R&D tax credit scheme.
Design optimization of the full-scale H2Neo carrier and containment tanks delivers material CAPEX and
OPEX savings.
The optimized design of the full-scale H2Neo carrier and containment tanks delivers substantial CAPEX and OPEX
savings. By employing updated construction methods and material selection, including carbon steel and stainless steel
liner plates, a remarkable 30% weight reduction has been achieved. The reduction allows for further optimization of
speed, power, and fuel consumption, translating to material fuel savings and emission reductions.
Moreover, the final tank design boasts an 8% increase in storage capacity to 450 tonnes, with potential further upsides
based on trading patterns and operational practices.
The lighter cargo tanks offer flexibility during installation, increasing competition among shipbuilders and potentially
reducing costs for buyers. Updated ship outline specifications are now being reviewed with a select group of yards with
the support of Clarksons appointed as our advisor.
www.provaris.energy
2
Quarterly Activities Report – March 2024
Illustration of Provaris’ H2Neo Compressed Hydrogen Carrier with twin hydrogen storage tanks
Third non-binding MOU signed with international energy company for development of hydrogen supply
to Europe
Following the two non-binding Memorandum of Understanding (MoU) signings in the December 2023 quarter, including
Uniper Global Commodities, the March quarter continued to attract increased attention from major energy players,
with a third non-binding MoU with a prominent international energy company.
Together, we will assess Provaris' complete hydrogen delivery chain, which includes Provaris’ proprietary and innovative
H2Neo carriers and H2Leo barge solutions designed for regional gaseous hydrogen delivery. Joint investigations are
scheduled for 2024, with any definitive project agreements to be appraised upon completion.
The growing interest in Provaris' hydrogen delivery value
chain, leveraging proprietary technology for compressed
hydrogen storage and marine transportation, stems from
the flexibility and simplicity of the unloading
infrastructure, suitable for various locations. Moreover,
utilizing regional supply sources results in lower delivered
costs when compared to other long-range bulk carrier
alternatives, further enhancing the attractiveness of
Provaris' solution.
With our third MOU, we are exploring how compressed
hydrogen can contribute to the large import requirement
of Northwest European ports. Our goal remains to offer
the most cost-effective compressed hydrogen supply for
regional volumes, aligning with market demand and
funding schemes to reduce investment risks.
Joint Development of import facility at Port of Rotterdam provides market access to Europe
The current quarter saw Provaris and GES enter into a collaboration agreement to develop a new hydrogen import
facility at the GES terminal in Rotterdam, the largest energy import terminal globally with 4.6Mt hydrogen import
required for 2030.
GES is a leading provider of innovative energy storage solutions, offering a comprehensive range of services to meet
the evolving needs of the energy industry, and is developing a multi-client, multi-product terminal in Rotterdam, able
to import both refrigerated ammonia and compressed hydrogen, with redeliveries into barges, rail, truck and the H2
grid (HyNetwork) operated by Gasunie.
Both parties believe the GES terminal in Rotterdam is an ideal site for bulk scale import of green hydrogen given the
early connection to the HyNetwork grid for gaseous supply to industrial users in the Port of Rotterdam and key
industrials users in Europe.
www.provaris.energy
3
Quarterly Activities Report – March 2024
Under the collaboration, GES and Provaris will complete a comprehensive prefeasibility study to demonstrate the
technical and economic viability of berthing and unloading of Provaris’ H2Neo compressed hydrogen carriers.
During 2024, prefeasibility studies will focus on the jetty facilities to discharge the H2Neo carrier, along with scavenging
compression, storage, HyNetwork grid connection, risk and safety, emissions, and other permitting and environmental
considerations. GES will finance, build, own and operate the terminal. Joint marketing of import capacity is underway
for operation in 2027/28.
GES Terminal Site at the Port of Rotterdam (Source: GES)
Peter Vucins, CEO of GES commented, “This
collaboration with Provaris showcases the types of
partnerships that GES is pursuing to facilitate the
Energy Transition through our contribution with
storage and logistics solutions, at Rotterdam as well
as other existing and future locations. I welcome the
opportunity to work closely with Provaris to develop a
cost competitive import solution for Rotterdam and
European energy customers.”
Partnership expanded with Norwegian Hydrogen across the Nordics
Post the quarter, Provaris expanded a Collaboration Agreement with Norwegian Hydrogen AS to jointly progress the
identification and development of several sites in the Nordic region for the large-scale production and export of
hydrogen to European markets.
Leveraging the past successes of our relationship the agreement aims to utilize locally available renewable energy
to produce hydrogen for shipment to European ports. This will assist energy-intensive industries in making an impact
on their decarbonization plans and target a scale and level of innovation that aligns with various European Union
funding schemes.
Under the agreement both parties will identify sites in the Nordic region for the potential joint development of
hydrogen production projects, for the export of hydrogen to Europe based on Provaris proprietary technology for the
storage and marine transportation of hydrogen in compressed form. The aim is to identify strategic locations for new
projects, in areas with robust grid and power supplies. These sites will facilitate the construction of state-of-the-art
electrolyzers, and hydrogen compression facilities linked to export jetties. Provaris’ H2Neo carriers will transport the
hydrogen, while the H2Leo barge will serve for storage. The initiatives will also foster circular economies by utilizing
by-products like clean oxygen and waste heat in local industries and district heating systems.
Jens Berge, Norwegian Hydrogen’s CEO
commented: “While we develop a
comprehensive network of production sites
and distribution infrastructure across the
entire Nordic region, to reduce emissions in
the Nordics, we have also identified several
sites with significant export potential.
While such locations could also be used to
produce other derivatives such as e-methanol
or green ammonia, we strongly believe that if
the end demand is for gaseous hydrogen,
nothing would be better than to avoid going
via a derivative solely for transportation
purposes. Provaris’ technology makes it
possible to bring hydrogen in gaseous form all
the way from production in the Nordics to the
customers in continental Europe.
www.provaris.energy
4
Quarterly Activities Report – March 2024
Completion of Prefeasibility and Collaboration with Gen2 Energy
During the quarter a Prefeasibility Study was finalised on the proposed Afjord project site in Norway. The study
raised no technical or economic issues to further assess the transport of green hydrogen from Afjord to a port in
central Europe.
Results of the study included various cases of hydrogen production of 22kpta to 66ktpa for export, resulting in a
range of delivered hydrogen prices of EUR 4.57 to 5.67 per kg.
Despite the competitive economic outcomes, when compared with a containerized shipping solution or alternative
carriers, and the potential for further development based on interest from German utilities seeking supply alternatives
from sites in Norway, no extension to the collaboration will be made at this time.
Attendance at World Hydrogen Summit 2024, Rotterdam, with Norwegian Delegation
From May 13-15, the Provaris team will be attending WHS 2024 and be included in the Norwegian Hydrogen Pavilion.
If you would like to arrange a meeting, please send a message to info@provaris.energy
General Meeting
Following shareholder approval at the General Meeting of Shareholders on 27 February 2024, the Company completed
Tranche 2 of the Placement announced on 30 November 2023 for $1.9 million. Tranche 2 of the Placement comprised
the issue of 5,750,000 ordinary shares to the Company’s directors who participated at an issue price of $0.04 per
share, raising $230,000.
Shareholders also approved the issue of 23,750,000 options attached to the Placement shares, which have an exercise
price of $0.075 per share and expiry date of 1 March 2026.
Board Change and Appointment of Product Development Director
As highlighted in the previous quarterly, this quarter saw founding shareholder and Executive Director of the Company
Garry Triglavcanin retire as a Director of the Board. Garry remains committed to the company with his appointment
to a new executive leadership role as Product Development Officer to focus on the development and optimisation of
our compressed hydrogen supply chain with a focus on the European stakeholders and technical due diligence.
Cash balance on 31 March 2024 was $1.67 million.
Refer to the separately released ASX Appendix 4C for further details. Total operating cash outflows have been reduced
from prior quarters.
The aggregate amount for payments to related parties and their associates included in item 6.1 in the Company’s ASX
Appendix 4C for the quarter ended 31 March 2024 was $181,000 comprising of fees, salaries and superannuation paid
to Directors, including Executive Directors.
- END –
This ASX announcement has been authorised by the Board of Provaris Energy Ltd.
To receive all company updates please
Norm Marshall
Company Secretary
+61 481 148629
nmarshall@provaris.energy
ASX.PV1
Martin Carolan
Managing Director & CEO
+61 404 809019
mcarolan@provaris.energy
@ProvarisEnergy
Melanie Singh
NWR Communications
+61 439 748 819
melanie@nwrcommunications.com.au
Provaris Energy Ltd.
info@provaris.energy
Perth | Sydney | Oslo
www.provaris.energy
5
Quarterly Activities Report – March 2024
About Provaris Energy
Provaris Energy Ltd (ASX: PV1) | www.provaris.energy
Provaris Energy (ASX: PV1) is an Australian public company developing a portfolio of integrated green hydrogen projects for the
regional trade of Asia and Europe, leveraging our innovative compressed hydrogen bulk storage and carrier. Our focus on value
creation through innovative development that aligns with our business model of simple and efficiency hydrogen production and
transport can establish an early-mover advantage for regional maritime trade of hydrogen and unlock a world of potential. In August
2022 Provaris Norway AS was established to advance the development of hydrogen export projects from Norway and other European
locations.
Disclaimer: This announcement may contain forward looking statements concerning projected costs, approval timelines,
construction timelines, earnings, revenue, growth, outlook or other matters (“Projections”). You should not place undue reliance on
any Projections, which are based only on current expectations and the information available to Provaris. The expectations reflected
in such Projections are currently considered by Provaris to be reasonable, but they may be affected by a range of variables that could
cause actual results or trends to differ materially, including but not limited to: price and currency fluctuations, the ability to obtain
reliable hydrogen supply, the ability to locate markets for hydrogen, fluctuations in energy and hydrogen prices, project site latent
conditions, approvals and cost estimates, development progress, operating results, legislative, fiscal and regulatory developments,
and economic and financial markets conditions, including availability of financing. Provaris undertakes no obligation to update any
Projections for events or circumstances that occur subsequent to the date of this announcement or to keep current any of the
information provided, except to the extent required by law. You should consult your own advisors as to legal, tax, financial and
related matters and conduct your own investigations, enquiries and analysis concerning any transaction or investment or other
decision in relation to Provaris. $ refers to Australian Dollars unless otherwise indicated.
www.provaris.energy
6
Rule 4.7B
Ap p e n d ix 4 C
Q u a rte rly ca sh flo w re p o rt fo r e n titie s
su b je ct to Listin g Ru le 4 .7 B
Na m e o f e n tity
Pro varis Ene rg y Ltd
ABN
Q u a rte r e n d e d (“cu rre n t q u a rte r”)
53 109 213 470
31 March 2024
Co n so lid a te d sta te m e n t o f ca sh flo w s
1.
Ca sh flo w s fro m o p e ra tin g a ctivitie s
1.1
Re ce ip ts fro m custo m e rs
1.2
Paym e nts fo r
Cu rre n t q u a rte r
$ A’0 0 0
Ye a r to d a te
(6 m o n th s)
$ A’0 0 0
-
-
(a)
re se arch and d e ve lo p m e nt
-
-
(b )
p ro d uct m anufacturing and o p e rating
co sts
-
-
(c)
ad ve rtising and m arke ting
(27)
(199)
(d )
le ase d asse ts
-
-
(e )
staff co sts
(622)
(1,928)
(f)
ad m inistratio n and co rp o rate co sts
(254)
(919)
-
-
13
62
1.3
Divid e nd s re ce ive d (se e no te 3)
1.4
Inte re st re ce ive d
1.5
Inte re st and o the r co sts o f finance p aid
-
-
1.6
Inco m e taxe s p aid
-
-
1.7
Go ve rnm e nt g rants and tax ince ntive s
-
-
1.81
O the r (R&D Re b ate Inco m e )
255
255
1.82
O the r (Pro je ct & IP d e ve lo p m e nt)
(313)
(2,468)
1 .9
Ne t ca sh fro m / (u se d in ) o p e ra tin g a ctivit ie s
(9 4 8 )
(5 ,1 9 7 )
2.
Ca sh flo w s fro m in ve stin g a ctivitie s
2.1
Paym e nts to acq uire o r fo r:
(a)
e ntitie s
-
-
(b )
b usine sse s
-
-
(c)
p ro p e rty, p lant and e q uip m e nt
-
-
(d )
inve stm e nts
-
-
(e )
inte lle ctual p ro p e rty
-
-
(f)
o the r no n-curre nt asse ts
-
-
ASX Listing Rule s Ap p e nd ix 4C (17/07/20)
+ Se e chap te r 19 o f the ASX Listing Rule s fo r d e fine d te rm s.
Pag e 1
Ap p e n d ix 4 C
Q u a rte rly ca sh flo w re p o rt fo r e n titie s su b je ct to Listin g Ru le 4 .7 B
Co n so lid a te d sta te m e n t o f ca sh flo w s
2.2
Cu rre n t q u a rte r
$ A’0 0 0
Ye a r to d a te
(6 m o n th s)
$ A’0 0 0
Pro ce e d s fro m d isp o sal o f:
(a)
e ntitie s
-
-
(b )
b usine sse s
-
-
(c)
p ro p e rty, p lant and e q uip m e nt
-
-
(d )
inve stm e nts
-
-
(e )
inte lle ctual p ro p e rty
-
-
(f)
o the r no n-curre nt asse ts
-
-
2.3
Cash flo ws fro m lo ans to o the r e ntitie s
-
-
2.4
Divid e nd s re ce ive d (se e no te 3)
-
-
2.5
O the r (p ro vid e d e tails if m ate rial)
-
-
2 .6
Ne t ca sh fro m / (u se d in ) in ve stin g a ctivit ie s
-
-
3.
Ca sh flo w s fro m fin a n cin g a ctivitie s
3.1
Pro ce e d s fro m issue s o f e q uity se curitie s
(e xclud ing co nve rtib le d e b t se curitie s)
128
1,775
3.2
Pro ce e d s fro m issue o f co nve rtib le d e b t
se curitie s
-
-
3.3
Pro ce e d s fro m e xe rcise o f o p tio ns
-
-
3.4
Transactio n co sts re late d to issue s o f e q uity
se curitie s o r co nve rtib le d e b t se curitie s
-
-
3.5
Pro ce e d s fro m b o rro wing s
-
-
3.6
Re p aym e nt o f b o rro wing s
-
-
3.7
Transactio n co sts re late d to lo ans and
b o rro wing s
-
-
3.8
Divid e nd s p aid
-
-
3.9
O the r (p ro vid e d e tails if m ate rial)
-
-
3 .1 0
Ne t ca sh fro m / (u se d in ) fin a n cin g a ctivitie s
-
-
4.
Ne t in cre a se / (d e cre a se ) in ca sh a n d ca sh
e q u iva le n ts fo r th e p e rio d
4.1
Cash and cash e q uivale nts at b e g inning o f
p e rio d
2,488
5,070
4.2
Ne t cash fro m / (use d in) o p e rating activitie s
(ite m 1.9 ab o ve )
(948)
(5,197)
4.3
Ne t cash fro m / (use d in) inve sting activitie s
(ite m 2.6 ab o ve )
-
-
4.4
Ne t cash fro m / (use d in) financing activitie s
(ite m 3.10 ab o ve )
128
1,775
4.5
Effe ct o f m o ve m e nt in e xchang e rate s o n cash
he ld
-
19
Ca sh a n d ca sh e q u iva le n ts a t e n d o f p e rio d
1 ,6 6 8
1 ,6 6 8
ASX Listing Rule s Ap p e nd ix 4C (17/07/20)
+ Se e chap te r 19 o f the ASX Listing Rule s fo r d e fine d te rm s.
Pag e 2
Ap p e n d ix 4 C
Q u a rte rly ca sh flo w re p o rt fo r e n titie s su b je ct to Listin g Ru le 4 .7 B
Cu rre n t q u a rte r
$ A’0 0 0
Pre vio u s q u a rte r
$ A’0 0 0
5.
Re co n cilia tio n o f ca sh a n d ca sh e q u iva le n ts
at the e nd o f the q uarte r (as sho wn in the
co nso lid ate d state m e nt o f cash flo ws) to the
re late d ite m s in the acco unts
5.1
Bank b alance s
1,668
2,488
5.2
Call d e p o sits
-
-
5.3
Bank o ve rd rafts
-
-
5.4
O the r (p ro vid e d e tails)
-
-
5 .5
Ca sh a n d ca sh e q u iva le n ts a t e n d o f q u a rte r
(sh o u ld e q u a l ite m 4 .6 a b o ve )
1,668
2,488
6.
Pa ym e n ts to re la te d p a rtie s o f th e e n tity a n d th e ir a sso cia te s
6.1
Ag g re g ate am o unt o f p aym e nts to re late d p artie s and the ir asso ciate s
includ e d in ite m 1
181
6.2
Ag g re g ate am o unt o f p aym e nts to re late d p artie s and the ir asso ciate s
includ e d in ite m 2
-
Cu rre n t q u a rte r
$ A' 0 0 0
No te : if any am o unts are sho wn in ite m s 6.1 o r 6.2, yo ur q uarte rly activity re p o rt m ust includ e a d e scrip tio n o f,
and an e xp lanatio n fo r, such p aym e nts
Ite m 6.1 includ e s fe e s, salarie s and sup e rannuatio n p aid to d ire cto rs, re lating to varying p e rio d s.
7.
Fin a n cin g fa cilitie s
Note : the te rm “facility’ includ e s all forms of
financing arrang e me nts availab le to the e ntity.
Am o u n t d ra w n a t
q u a rte r e n d
$ A’0 0 0
To ta l fa cility a m o u n t
a t q u a rte r e n d
$ A’0 0 0
Ad d note s as ne ce ssary for an und e rstand ing of
the source s of finance availab le to the e ntity.
7.1
Lo an facilitie s
-
-
7.2
Cre d it stand b y arrang e m e nts
-
-
7.3
O the r (p le ase sp e cify)
-
-
7.4
To ta l fin a n cin g fa cilitie s
-
-
7.5
Un u se d fin a n cin g fa cilitie s a va ila b le a t q u a rte r e n d
7.6
Includ e in the b o x b e lo w a d e scrip tio n o f e ach facility ab o ve , includ ing the le nd e r, inte re st rate ,
m aturity d ate and whe the r it is se cure d o r unse cure d . If any ad d itio nal financing facilitie s have b e e n
e nte re d into o r are p ro p o se d to b e e nte re d into afte r q uarte r e nd , includ e a no te p ro vid ing d e tails
o f tho se facilitie s as we ll.
-
N/a
ASX Listing Rule s Ap p e nd ix 4C (17/07/20)
+ Se e chap te r 19 o f the ASX Listing Rule s fo r d e fine d te rm s.
Pag e 3
Ap p e n d ix 4 C
Q u a rte rly ca sh flo w re p o rt fo r e n titie s su b je ct to Listin g Ru le 4 .7 B
8.
Estim a te d ca sh a va ila b le fo r fu tu re o p e ra tin g a ctivitie s
$ A’0 0 0
8.1
Ne t cash fro m / (use d in) o p e rating activitie s (ite m 1.9)
(948)
8.2
Cash and cash e q uivale nts at q uarte r e nd (ite m 4.6)
1,668
8.3
Unuse d finance facilitie s availab le at q uarte r e nd (ite m 7.5)
8.4
To tal availab le fund ing (ite m 8.2 + ite m 8.3)
8.5
Estim a te d q u a rte rs o f fu n d in g a va ila b le (ite m 8 .4 d ivid e d b y
ite m 8 .1 )
1,668
1.8
Note : if the e ntity has re p orte d p ositive ne t op e rating cash flows in ite m 1.9, answe r ite m 8.5 as
“N/A”. O the rwise , a fig ure for the e stimate d q uarte rs of fund ing availab le must b e includ e d in
ite m 8.5.
8.6
If ite m 8.5 is le ss than 2 q uarte rs, p le ase p ro vid e answe rs to the fo llo wing q ue stio ns:
8.6.1
Do e s the e ntity e xp e ct that it will co ntinue to have the curre nt le ve l o f ne t o p e rating cash
flo ws fo r the tim e b e ing and , if no t, why no t?
Answe r: Ye s.
8.6.2
Has the e ntity take n any ste p s, o r d o e s it p ro p o se to take any ste p s, to raise furthe r cash to
fund its o p e ratio ns and , if so , what are tho se ste p s and ho w like ly d o e s it b e lie ve that the y
will b e succe ssful?
Answe r: The Co m p any co ntinue s to p ro g re ss alte rnative fund ing and cap ital raising o p tio ns e ithe r
at the sub sid iary le ve l o r p are nt Co m p any le ve l, includ ing no n-d ilutive so urce s o f fund s
availab le fro m inno vatio n and R&D so ft fund ing sche m e s. The Co m p any re m ains co nfid e nt
o f co m p le ting furthe r fund ing /cap ital raising re q uire d (b ase d o n all p re vio us succe ssful
cap ital raising s).
The co m p any has cap acity to d e fe r o r cance l d iscre tio nary p ro je ct and R&D e xp e nd iture if
re q uire d .
8.6.3
Do e s the e ntity e xp e ct to b e ab le to co ntinue its o p e ratio ns and to m e e t its b usine ss
o b je ctive s and , if so , o n what b asis?
Answe r: Ye s. The Co m p any re m ains co nfid e nt in its ab ility to raise furthe r fund ing /cap ital and
m anag e its cash p o sitio n and o utflo ws, witho ut ne g ative ly im p acting o n its curre nt
b usine ss and o p e rating o b je ctive s.
Note : whe re ite m 8.5 is le ss than 2 q uarte rs, all of q ue stions 8.6.1, 8.6.2 and 8.6.3 ab ove must b e
answe re d .
Co m p lia n ce sta te m e n t
1
This state m e nt has b e e n p re p are d in acco rd ance with acco unting stand ard s and p o licie s which
co m p ly with Listing Rule 19.11A.
2
This state m e nt g ive s a true and fair vie w o f the m atte rs d isclo se d .
Date :
____30 Ap ril 2024_____________
Autho rise d b y:
_____Martin Caro lan_______________
(Nam e o f b o d y o r o ffice r autho rising re le ase – se e no te 4)
ASX Listing Rule s Ap p e nd ix 4C (17/07/20)
+ Se e chap te r 19 o f the ASX Listing Rule s fo r d e fine d te rm s.
Pag e 4
Ap p e n d ix 4 C
Q u a rte rly ca sh flo w re p o rt fo r e n titie s su b je ct to Listin g Ru le 4 .7 B
No te s
1.
This q uarte rly cash flo w re p o rt and the acco m p anying activity re p o rt p ro vid e a b asis fo r info rm ing the m arke t ab o ut
the e ntity’s activitie s fo r the p ast q uarte r, ho w the y have b e e n finance d and the e ffe ct this has had o n its cash p o sitio n.
An e ntity that wishe s to d isclo se ad d itio nal info rm atio n o ve r and ab o ve the m inim um re q uire d und e r the Listing Rule s
is e nco urag e d to d o so .
2.
If this q uarte rly cash flo w re p o rt has b e e n p re p are d in acco rd ance with Australian Acco unting Stand ard s, the
d e finitio ns in, and p ro visio ns o f, AASB 107: State me nt of Cash Flows ap p ly to this re p o rt. If this q uarte rly cash flo w
re p o rt has b e e n p re p are d in acco rd ance with o the r acco unting stand ard s ag re e d b y ASX p ursuant to Listing
Rule 19.11A, the co rre sp o nd ing e q uivale nt stand ard ap p lie s to this re p o rt.
3.
Divid e nd s re ce ive d m ay b e classifie d e ithe r as cash flo ws fro m o p e rating activitie s o r cash flo ws fro m inve sting
activitie s, d e p e nd ing o n the acco unting p o licy o f the e ntity.
4.
If this re p o rt has
Share your feedback
Discover